The Belmont Conservation Commission
Denies Notice of Intent
On June 23, 2003, the Belmont Conservation Commission issued a denial O'Neill Properties' request for a Notice of Intent in order to proceed with the development of a 250,000 square foot research and development office building at the Belmont Uplands. This request was denied because the applicant did not submit sufficient information to describe the site, the work, or the effect of the work on the interests identified in the Wetlands Protection Act. The Commission setforth an Order of Conditions that details the denial of the Notice of Intent. For furthin information on this Notice of
Intent please contact Glenn Clancy or Tim Higgins at the Office of Community Development
|  |